Purchase of induction melting furnace users need to bring their own projects
1. High-voltage power supply conditions: including high-voltage switchgear, power transformers and cables;
2. Low-voltage power supply conditions: including low-voltage power distribution cabinets (screens) and cables;
3. The IF power cabinet is output to the capacitor bank busbar;
4. a capacitor bank rack to a channel busbar at a water-cooled cable joint;
5. Cooling water circulation pool for induction melting furnace
1) when not adding water tower: not less than l00m3, depth 1. 5-2m;
2) When adding water tower: According to the heat exchange capacity of the water tower, the heat exchange capacity per hour is about 150,000 kcal;
6. Water pump: It is recommended to use double pump and double motor, pump head ≥30m, flow rate ≥300L/min; (20M3/h)
7. The main water inlet pipe: caliber ≥ 3 inches, the water distribution pipeline is 1. 5-2.5 inches;
8. The backwater main pipe: caliber ≥ 4 inches, the water conduit is 2. 5-3 inches;
Water system reference supplier water system diagram implementation
9. Infrastructure construction: the implementation of the basic conditions of the supplier;
10. Furnace lining material: generally quartz sand material, see supplier's instruction manual;